IMS-WI-39 AIB Operations Project Co-ordinators Meeting Daily Tasks

These tasks must be completed prior to leaving the office of assigned meeting days

Written by: JM
Date: 06/2017
Approved: AG
  1. 1

    Update All Jobs

    Updates must be done on all jobs every week, this includes jobs with no or little change. There are 2 main options for doing this
    1. Update each job manually yourself
    2. View list of all jobs and voice record all updates, email voice files to osclaims@aizer.com.au
    These updates are to be marked as public and should include
    • any recent progress
    • planned progress
    • and changes to works being completed
    • should state if customer has been spoken to in previous week and if not why not
  2. 2

    Action Invoices

    All invoices that have been assigned for your review must be completed, invoices should not be approved unless
    • Assigned work has been completed and checked
    • Amount invoiced does not exceed the purchase order amount
    • You are willing to put your name to the work completed by this contractor
    Invoices not meeting these standards should be marked as rejected with any required comments added

    sweetprocess.com/procedures/14046/approving-in...
  3. 3

    Update % complete

    Open the report aizer.quickbase.com/db/bgm8iwb93?a=q&qid=163

    select grid edit and then enter a % complete against each item, be accurate as this field is used by accounts to forecast financials   
  4. 4

    Confirm Job Timeframes

    Update all completion dates in the schedule section of each project, this information must be accurate as it is used for the following things
    • Update sent to provider and from there passed to home owner
    • Accounts use information to work out who / what and when can be paid to contractors and suppliers
    • Timeframe's are strictly monitored by insurers and effect job allocations 
    This is done separately from the project review meeting had with the Operations Manager 
  5. 5

    Clear Case Manager Contact List

    When contacting customers ensure to place a date of contact in the 'Contact follow up' column.  Contact with the insured is required at least once every 10 days.
  6. 6

    Follow up all Variations

    Discuss all variations with the related estimator, these points need to be remembered
    • Repair Timeframes do not stop to allow for variations
    • At all time the project is yours and you need to drive the outcomes
    • Variations don't make money so need to be actioned and completed quickly
  7. 7

    Confirm all New Jobs actioned

    Check that all newly assigned jobs have had all required actions taken, this includes
    • Site meeting with client
    • Quote Requests sent
    • Scope confirmed
    • Schedule Completed
    • Purchase Orders sent
    • Trade requests made
  8. 8

    Project Review Meeting

    Following on from the above step you will need to meet with the Operations Manager to review progress of all jobs